Animal Production & Protection
Crop Production and Protection
Nutrition, Food Safety / Quality
Natural Resources and Sustainable Agricultural
Systems
Ad Hoc Review Sessions
APP
APP NP 101 Food Animal Production: 29 Projects
Task
Due Date
Concurrence Memo to AD
20-Aug-2021
PDRAM
03-Sep-2021
COIs to OSQR
17-Sep-2021
Plans to Area
26-Nov-2021
Plans to ONP
07-Jan-2022
ONP Validates
04-Feb-2022
Plans to OSQR
04-Mar-2022
Review Period Start
05-Mar-2022
Review Period End
03-Jun-2022
Implementation
01-Sep-2022
Termination
12-Feb-2028
APP NP 103 Animal Health: 36 Projects
Task
Due Date
Concurrence Memo to AD
03-Nov-2020
PDRAM
17-Nov-2020
COIs to OSQR
01-Dec-2020
Plans to Area
09-Feb-2021
Plans to ONP
23-Mar-2021
ONP Validates
20-Apr-2021
Plans to OSQR
18-May-2021
Review Period Start
19-May-2021
Review Period End
17-Aug-2021
Implementation
15-Nov-2021
Termination
28-Apr-2027
APP NP 104 Veterinary, Medical and Urban Entomology: 11 Projects
Task
Due Date
Concurrence Memo to AD
06-Sep-2018
PDRAM
20-Sep-2018
COIs to OSQR
04-Oct-2018
Plans to Area
13-Dec-2018
Plans to ONP
24-Jan-2019
ONP Validates
21-Feb-2019
Plans to OSQR
21-Mar-2019
Review Period Start
22-Mar-2019
Review Period End
20-Jun-2019
Implementation
18-Sep-2019
Termination
28-Feb-2025
APP NP 106 Aquaculture: 17 Projects
Task
Due Date
Concurrence Memo to AD
30-Nov-2018
PDRAM
14-Dec-2018
COIs to OSQR
28-Dec-2018
Plans to Area
08-Mar-2019
Plans to ONP
19-Apr-2019
ONP Validates
17-May-2019
Plans to OSQR
14-Jun-2019
Review Period Start
15-Jun-2019
Review Period End
13-Sep-2019
Implementation
12-Dec-2019
Termination
24-May-2025
CPP
CPP NP 301A Plant Genetic Resources, Genomics, and Genetic Improvement: 52 Projects
Task
Due Date
Concurrence Memo to AD
17-Jan-2017
PDRAM
31-Jan-2017
COIs to OSQR
14-Feb-2017
Plans to Area
25-Apr-2017
Plans to ONP
06-Jun-2017
ONP Validates
04-Jul-2017
Plans to OSQR
01-Aug-2017
Review Period Start
02-Aug-2017
Review Period End
28-Feb-2018
Implementation
29-May-2018
Termination
12-Jul-2023
CPP NP 301B Plant Genetic Resources, Genomics, and Genetic Improvement: 52 Projects
Task
Due Date
Concurrence Memo to AD
17-Feb-2017
PDRAM
03-Mar-2017
COIs to OSQR
17-Mar-2017
Plans to Area
26-May-2017
Plans to ONP
07-Jul-2017
ONP Validates
04-Aug-2017
Plans to OSQR
01-Sep-2017
Review Period Start
02-Sep-2017
Review Period End
28-Feb-2018
Implementation
29-May-2018
Termination
12-Aug-2023
CPP NP 301C Plant Genetic Resources, Genomics, and Genetic Improvement: 51 Projects
Task
Due Date
Concurrence Memo to AD
20-Mar-2017
PDRAM
03-Apr-2017
COIs to OSQR
17-Apr-2017
Plans to Area
26-Jun-2017
Plans to ONP
07-Aug-2017
ONP Validates
04-Sep-2017
Plans to OSQR
02-Oct-2017
Review Period Start
03-Oct-2017
Review Period End
28-Feb-2018
Implementation
29-May-2018
Termination
12-Sep-2023
CPP NP 303 Plant Diseases: 46 Projects
Task
Due Date
Concurrence Memo to AD
26-Feb-2021
PDRAM
12-Mar-2021
COIs to OSQR
26-Mar-2021
Plans to Area
04-Jun-2021
Plans to ONP
16-Jul-2021
ONP Validates
13-Aug-2021
Plans to OSQR
10-Sep-2021
Review Period Start
11-Sep-2021
Review Period End
27-Oct-2021
Implementation
25-Jan-2022
Termination
21-Aug-2027
CPP NP 304A Crop Production and Quarantine: 26 Projects
Task
Due Date
Concurrence Memo to AD
01-Jul-2019
PDRAM
15-Jul-2019
COIs to OSQR
29-Jul-2019
Plans to Area
07-Oct-2019
Plans to ONP
18-Nov-2019
ONP Validates
16-Dec-2019
Plans to OSQR
13-Jan-2020
Review Period Start
14-Jan-2020
Review Period End
13-Apr-2020
Implementation
12-Jul-2020
Termination
23-Dec-2025
CPP NP 304B Plant Production and Quarantine: 42 Projects
Task
Due Date
Concurrence Memo to AD
19-Aug-2019
PDRAM
02-Sep-2019
COIs to OSQR
16-Sep-2019
Plans to Area
25-Nov-2019
Plans to ONP
06-Jan-2020
ONP Validates
03-Feb-2020
Plans to OSQR
02-Mar-2020
Review Period Start
03-Mar-2020
Review Period End
01-Jun-2020
Implementation
30-Aug-2020
Termination
10-Feb-2026
CPP NP 305 Crop Production: 25 Projects
Task
Due Date
Concurrence Memo to AD
20-Nov-2018
PDRAM
04-Dec-2018
COIs to OSQR
18-Dec-2018
Plans to Area
26-Feb-2019
Plans to ONP
09-Apr-2019
ONP Validates
07-May-2019
Plans to OSQR
04-Jun-2019
Review Period Start
05-Jun-2019
Review Period End
03-Sep-2019
Implementation
02-Dec-2019
Termination
14-May-2025
NFSQ
NFSQ NP 107A Human Nutrition: 30 Projects
Task
Due Date
Concurrence Memo to AD
15-Feb-2018
PDRAM
01-Mar-2018
COIs to OSQR
15-Mar-2018
Plans to Area
24-May-2018
Plans to ONP
05-Jul-2018
ONP Validates
02-Aug-2018
Plans to OSQR
30-Aug-2018
Review Period Start
31-Aug-2018
Review Period End
29-Nov-2018
Implementation
27-Feb-2019
Termination
09-Aug-2024
NFSQ NP 107B Human Nutrition: 30 Projects
Task
Due Date
Concurrence Memo to AD
19-Mar-2018
PDRAM
02-Apr-2018
COIs to OSQR
16-Apr-2018
Plans to Area
25-Jun-2018
Plans to ONP
06-Aug-2018
ONP Validates
03-Sep-2018
Plans to OSQR
01-Oct-2018
Review Period Start
02-Oct-2018
Review Period End
31-Dec-2018
Implementation
31-Mar-2019
Termination
10-Sep-2024
NFSQ NP 108 Food Safety (Animal and Plant Products): 64 Projects
Task
Due Date
Concurrence Memo to AD
29-Jan-2020
PDRAM
12-Feb-2020
COIs to OSQR
26-Feb-2020
Plans to Area
06-May-2020
Plans to ONP
17-Jun-2020
ONP Validates
15-Jul-2020
Plans to OSQR
12-Aug-2020
Review Period Start
13-Aug-2020
Review Period End
25-Jan-2021
Implementation
24-Feb-2021
Termination
23-Jul-2026
NFSQ NP 306A Quality and Utilization of Agricultural Products: 36 Projects
Task
Due Date
Concurrence Memo to AD
20-Mar-2019
PDRAM
03-Apr-2019
COIs to OSQR
17-Apr-2019
Plans to Area
26-Jun-2019
Plans to ONP
07-Aug-2019
ONP Validates
04-Sep-2019
Plans to OSQR
02-Oct-2019
Review Period Start
03-Oct-2019
Review Period End
01-Jan-2020
Implementation
31-Mar-2020
Termination
11-Sep-2025
NFSQ NP 306B Quality and Utilization of Agricultural Products: 37 Projects
Task
Due Date
Concurrence Memo to AD
30-Apr-2019
PDRAM
14-May-2019
COIs to OSQR
28-May-2019
Plans to Area
06-Aug-2019
Plans to ONP
17-Sep-2019
ONP Validates
15-Oct-2019
Plans to OSQR
12-Nov-2019
Review Period Start
13-Nov-2019
Review Period End
11-Feb-2020
Implementation
11-May-2020
Termination
22-Oct-2025
NRSAS
NRSAS NP 211 Water Availability and Watershed Management: 33 Projects
Task
Due Date
Concurrence Memo to AD
15-Jan-2021
PDRAM
29-Jan-2021
COIs to OSQR
12-Feb-2021
Plans to Area
23-Apr-2021
Plans to ONP
04-Jun-2021
ONP Validates
02-Jul-2021
Plans to OSQR
30-Jul-2021
Review Period Start
31-Jul-2021
Review Period End
29-Oct-2021
Implementation
27-Jan-2022
Termination
10-Jul-2027
NRSAS NP 212 Soil and Air: 26 Projects
Task
Due Date
Concurrence Memo to AD
21-Jul-2020
PDRAM
04-Aug-2020
COIs to OSQR
18-Aug-2020
Plans to Area
27-Oct-2020
Plans to ONP
08-Dec-2020
ONP Validates
05-Jan-2021
Plans to OSQR
02-Feb-2021
Review Period Start
03-Feb-2021
Review Period End
04-May-2021
Implementation
02-Aug-2021
Termination
13-Jan-2027
NRSAS NP 213 Biorefining: 9 Projects
Task
Due Date
Concurrence Memo to AD
04-Oct-2018
PDRAM
18-Oct-2018
COIs to OSQR
01-Nov-2018
Plans to Area
10-Jan-2019
Plans to ONP
21-Feb-2019
ONP Validates
21-Mar-2019
Plans to OSQR
18-Apr-2019
Review Period Start
19-Apr-2019
Review Period End
18-Jul-2019
Implementation
16-Oct-2019
Termination
28-Mar-2025
NRSAS NP 215 Pasture, Forage and Rangeland Systems: 26 Projects
Task
Due Date
Concurrence Memo to AD
12-Jan-2018
PDRAM
26-Jan-2018
COIs to OSQR
09-Feb-2018
Plans to Area
20-Apr-2018
Plans to ONP
01-Jun-2018
ONP Validates
29-Jun-2018
Plans to OSQR
27-Jul-2018
Review Period Start
28-Jul-2018
Review Period End
26-Oct-2018
Implementation
24-Jan-2019
Termination
06-Jul-2024
NRSAS NP 216 Agricultural System Competitiveness and Sustainability: 26 Projects
Task
Due Date
Concurrence Memo to AD
02-Oct-2017
PDRAM
16-Oct-2017
COIs to OSQR
30-Oct-2017
Plans to Area
08-Jan-2018
Plans to ONP
19-Feb-2018
ONP Validates
19-Mar-2018
Plans to OSQR
16-Apr-2018
Review Period Start
17-Apr-2018
Review Period End
16-Jul-2018
Implementation
14-Oct-2018
Termination
26-Mar-2024
Ad Hoc Review Sessions
AdHoc NP AdHoc June Varies: Varies Projects
Task
Due Date
Concurrence Memo to AD
17-Nov-2017
PDRAM
01-Dec-2017
COIs to OSQR
15-Dec-2017
Plans to Area
23-Feb-2018
Plans to ONP
06-Apr-2018
ONP Validates
04-May-2018
Plans to OSQR
01-Jun-2018
Review Period Start
02-Jun-2018
Review Period End
15-Sep-2018
Implementation
14-Nov-2018
Termination
11-May-2024
AdHoc NP AdHoc Dec Varies: Varies Projects
Task
Due Date
Concurrence Memo to AD
18-May-2018
PDRAM
01-Jun-2018
COIs to OSQR
15-Jun-2018
Plans to Area
24-Aug-2018
Plans to ONP
05-Oct-2018
ONP Validates
02-Nov-2018
Plans to OSQR
30-Nov-2018
Review Period Start
01-Dec-2018
Review Period End
16-Mar-2019
Implementation
15-May-2019
Termination
09-Nov-2024